Priority | Foster a culture of high purpose, accountability & accomplishment |
| Create a five year capital investment plan for facilities and infrastructure
|
Q1 |
Lewis |
 |
Realization 1 |
Communicated to main campus the project list for facilities and IT for forwarding to HEPC. New project will be initiated based on strategic planning initiatives for HSC Schools.
|
| Build case statements for the HSC portion of the WVU capital campaign
|
Q1 |
Phalunas |
 |
Realization 1 |
|
| Prioritize and implement initiatives identified by the "Cost Savings" group
|
FY2013 |
Phillips |
 |
Realization 1 |
Computer purchasing procedures and computer in service extension pilot programs have been put into place. Other cost savings initiatives have been put in place including: refinancing of the Energy Performance Phase III/Siemens, inventory reduction, recycling used furniture, landscaping contracts, vehicle fleet reduction, and dental clinical supply purchases. Targets for Q4 include: develop, review RFP for Cost Savings Consultant, schedule and hold town hall discussions, identify & define mechanism to implement piloted initiatives HSC wide.
|
| Require all support units to develop, implement, and report a minimum of three service level standards (Finance, HR, Facilities, Legal)
|
Q4 |
Miele |
 |
Realization 3 |
Service levels standards have been developed for legal, facilities, IT, risk management, project management, and research. Results will be reported on a quarterly basis.
|
| Ensure all HSC Schools develop strategic plans in direct support of HSC Plan
|
Q1 |
Miele |
 |
Realization 3 |
All HSC Schools have submitted strategic plans. These plans are posted at the following link. http://www.hsc.wvu.edu/hsc2020/hsc-plans
|
| In conjunction with main campus the implementation of e-business suite
|
FY2013 |
Linger |
 |
Realization 1 |
There are two parts to the Oracle project. Part one is OBIEE to replace Discoverer. The official kickoff is 5/1. Part two of the project is the Oracle e-Business suite upgrade. This is scheduled to ramp up later in the summer 2012.
|
| Facilities space review and reassignment guidelines development
|
FY2013 |
Butcher |
 |
Realization 1 |
|
| Implementation of project management software
|
Q4 |
Miele |
 |
Realization 1 |
Software has been selected, purchased, designed, and tested. In process of developing training material.
|
| Development of guidelines for the establishment of centers and institutes at HSC
|
Q4 |
Miele |
 |
Realization 1 |
Draft guidelines have been developed. Further input from HSC leadership and faculty will be required prior to finalization.
|